Monday, April 9, 2007

Insulation

Not much happened last week, except for the inspector's visit and a few minor corrections.
Here are the inspector's comments:
------------------------------------------------
BUILDING: Girder support - Girder above stairway and ? front door header
HEATING: 4/5/07
PLUMBING: 4/5/07
ELECTRICAL: 4/5/07
INSULATION:
UNDERGROUND:
INSPECTORS REMARKS: Garage door LVL needs lateral support. Need ladder to get into basement to check Building.
-----------------------------------------------
Today the insulation was put in all of the walls (including the garage), which were then covered in clear plastic. The water/ice/slush was pumped out of the basement and the sump pump and piping was installed.

Sorry, I didn't have my camera today, I will make sure to bring it tomorrow.

Wednesday, April 4, 2007

Inspections

Nothing photo-worthy today... most of the changes were fix-ups for the inspection. The blanket of straw on the basement floor was raked out, so they must be preparing to pour a floor soon. They'll have some standing water to deal with first, though.

Monday, April 2, 2007

Plumbing, Electric, Speakers!