Wednesday, June 6, 2007

New Finish Date

We met with Brett and the concrete guy today to plan out the driveway and sidewalk. They will pour it on Thursday as long as it isn't going to rain all day. The final grading of the lot should be done this week. The countertops should be delivered and installed either today or tomorrow. We have a new finish carpenter who will be building the lockers, columns on the front exterior, and anything else that comes up. The stone on the outside of the house and the rest of the siding should be done next Monday. Basemen Flooring will be back next week Wednesday to apply the final coat on the wood floors. The carpet will be put in next Thursday, as will the appliances. Cleaning will be done on Friday, and we should have an occupancy permit by next Friday evening (the 15th). This is 5 days later than we thought, but not too bad as long as it actually happens that way.